Tracking sewing floor output in pieces works fine if every line makes the exact same plain T-shirt. Once one line runs crew tees while the next sews lined denim jackets, raw piece counts stop telling the truth. Ten thousand jackets take far more sewing time than ten thousand tees. Standard Allowed Hours, or SAH, puts every garment style on one shared time clock so planners can compare lines fairly.
Factory planners, IE teams, and plant owners use SAH every week to book lines, check daily output, and track labor cost per hour. Once you know the SMV of a style, getting SAH takes only a few seconds.
What SAH means on the sewing floor
SAH stands for Standard Allowed Hours. It is the standard time, in hours, that a trained operator needs to sew one full garment at normal speed, with rest and machine allowances built in.
Standard Minute Value (SMV) measures that same standard work in minutes. So SAH is just SMV divided by 60. If your IE desk has not timed the style yet, check our Standard Minute Value (SMV) Calculation Guide first.
Four SAH formulas used in daily planning
Most factory planning boards run on four short equations:
SAH per garment = SMV ÷ 60
Produced SAH (earned hours) = Output pieces × SAH per garment
Available hours = Number of operators × Shift hours
Line efficiency (%) = (Produced SAH ÷ Available hours) × 100
Keep earned hours separate from paid hours in every daily review. Produced SAH counts only the standard hours earned on good pieces that passed end-of-line QC. Available hours count the real clock time the factory paid for on that shift. Divide earned hours by paid hours and you get true line efficiency.
Checking one real sewing shift
Say Line 4 sews a cotton polo shirt with an SMV of 15.0 minutes. Thirty-six operators work an 8-hour shift, and end-of-line QC passes 720 good shirts by closing time.
First divide 15.0 by 60 to get 0.25 SAH per shirt. Multiply 720 passed shirts by 0.25, and Line 4 earned 180.0 Produced SAH for the shift. Meanwhile, 36 operators times 8 hours equals 288.0 Available hours. Divide 180.0 by 288.0 and multiply by 100. Line 4 ran at 62.5 percent efficiency.
Now look at Line 5 across the aisle. Suppose Line 5 ran a plain 6-minute basic tee (0.10 SAH) and packed 1,600 pieces with the same 36 crew members. On piece counts alone, Line 5 looks more than twice as strong. Switch to SAH, though, and Line 5 earned just 160 SAH against Line 4's 180 SAH. Using SAH stops easy styles from making slower lines look better than they really are.
Booking bulk orders and ship dates with SAH
Suppose merchandising asks if your plant can take a 24,000-piece polo order (0.25 SAH each) for shipment next month. Multiply order qty by SAH per garment to see total labor needed:
Required SAH = 24,000 x 0.25 = 6,000 SAH
We just saw that one 36-operator line at 62.5 percent efficiency produces 180 SAH a day (36 x 8 x 0.625). Divide 6,000 by 180, and one line needs 33.3 work days to clear the order. Put three matching lines on the style and bulk sewing drops to 11.1 days, plus two or three extra days for line setup and learning curve ramp-up. You can verify daily piece targets and crew counts fast with our Production Target Calculator and Line Efficiency Calculator.
Quick SMV to SAH and daily target table
A 35-operator sewing line on an 8-hour shift (280 available hours) at 60 percent efficiency earns 168 SAH each day. The table below turns common garment SMVs into SAH per piece and daily output targets at that load.
Garment style | Typical SMV | SAH per piece | Daily target (35 ops, 8 h, 60% eff) |
|---|---|---|---|
Basic crew-neck T-shirt | 6.0 min | 0.100 SAH | 1,680 pcs/day |
Basic knitted polo shirt | 15.0 min | 0.250 SAH | 672 pcs/day |
Woven long-sleeve dress shirt | 22.0 min | 0.367 SAH | 458 pcs/day |
Five-pocket denim jean | 25.0 min | 0.417 SAH | 403 pcs/day |
Fleece zip hoodie | 30.0 min | 0.500 SAH | 336 pcs/day |
Lined casual jacket | 45.0 min | 0.750 SAH | 224 pcs/day |
How accounts tracks Cost per SAH
Finance teams pair monthly plant spend with SAH to test whether buyer CM rates cover real factory bills. Add up all monthly factory costs (sewing wages, helpers, supervisors, rent, power, repairs, and office pay) and divide by total Produced SAH for the month:
Cost per SAH = Total monthly factory cost / Total monthly produced SAH
Say a plant spends $180,000 in a month and makes 45,000 SAH across all lines. Its Cost per SAH sits at $4.00. For our 0.25 SAH polo shirt, break-even Cut and Make (CM) cost is $4.00 times 0.25, or $1.00 before profit margin.
Three habits that distort SAH reports
A few casual floor habits skew SAH sheets fast. First, keep your headcount rule steady all year. Pick whether available hours count sewing operators only or operators plus helpers, and do not switch mid-season or your monthly chart becomes useless.
Second, avoid loading lines off a tight buyer-quoted SMV when real sewing takes longer. Buyers squeeze quoted SMV down during price talks, yet adding a heavy pocket or tricky placket burns real minutes at the machine. Track quoted SAH and floor SAH side by side so accounts sees margin loss while planners guard ship dates. Last, never leave overtime hours out of available time. If 36 operators stay two extra hours, available hours move from 288 to 360. Skipping overtime makes efficiency look high on paper while payroll eats profit.