Expediting Cost Benefit Analysis for Late Trims
Build an expediting decision from the actual line-readiness deadline, action-specific delay probabilities and incremental recovery costs. A worked trims example calculates the premium's break-even probability reduction and records the evidence, approval owner and fallback needed